Meeting with CPED this morning

We met with representatives from CPED this morning in an effort to learn about how to acquire a lot for the Appleseed House project. I summarized the procedure as I understand it based on today’s meeting below:

Generic CPED Procedure for purchasing a City-owned lot, as recorded on 12-2-2008

 

  • Make an offer to purchase, attach financing
  • CPED has a list of available lots, if needed
  • Select a general contractor (not mandatory)
  • Pick a lot
  • Submit site plan on survey, floor plans, and elevations for a schematic design review
  • Select a buyer (not mandatory)
  • CPED to notify neighborhood group of purchase
  • Neighborhood group has 45 days to deliberate and comment to CPED
  • CPED writes report for City Council’s Development Committee. Meetings will include the neighborhood group and council member
  • City Council has 10 days for a review
  • Documents are presented to the Mayor for signature
  • Deposit a check for the purchase
  • Work with real estate staff on questions or concerns
  • Signing of redevelopment contract
  • Outline time frame for project from start to finish
  • Closing

 

Typical process lasts 90 days from start to finish, including 45 days of neighborhood review.